Thursday, January 4, 2018 - 8:00am

WHAT: Temporary Street Closure on Deborah Drive at Claiborne Drive WHEN: Saturday, January 6, 2018 for up to the next 90 days

WHY: Drainage Pipe Replacement

Beginning at Noon on Saturday, January 6, 2018 for approximately the next 90 days, Deborah Drive will be closed to thru traffic West of Claiborne Drive due to drainage repairs. This is a complete 24/7 closure. The drainage replacement project consist of the removal of the existing 60" x 80" arch pipe and the Installation of a new 60" x 80" arch pipe. Detour signs are in place to redirect traffic.

View a map of the area

Contractor: CW&W Contractors, Inc.
Engineer: David Dumas
Contact: Arthur Holland, Project Manager, City of Monroe – Phone # 318.376.1346